SoPa plans a branded range of dips to sell through other retailers. The exam follows the range from the choice between making it in-house or outsourcing, through budgets and costing for a new production facility, to its early months of variances and KPIs.

Updated · Examiner's report pp322–328

Tasks
4
Sub-tasks
12
Topics
8
Pre-seen
SoPa

Task 1

Trigger: Senior management must decide whether SoPa makes the dips in a small facility of its own or buys them in from an outside producer. A chart of profit against volume compares the two, and weighted benefit scoring is proposed to help make the call.

  1. (a) Interpret40% of the task

    Core activity E: Short-term decisions
    What it asked
    Read the chart for both options: budgeted profit, fixed cost, average variable cost per unit, break-even point and margin of safety.
    Stronger answers
    Picked out profit, fixed cost and break-even for each option, explained how variable cost per unit and margin of safety are read from the chart without working them out, and compared the two options with reasons for the gaps.
    Weaker answers
    Described the chart in general terms, named a few elements such as fixed cost, and never compared in-house with outsourcing.
    Practise it in Tendra Tents: Kestrel contract: interpreting the break-even information
  2. (b) Discuss32% of the task

    Core activity E: Short-term decisions
    What it asked
    The benefits and limitations of this break-even analysis.
    Stronger answers
    Made three or four points, with at least one benefit and one limitation, each tied back to the chart and the dips decision.
    Weaker answers
    Gave short textbook benefits and limitations with no link to the chart or the scenario.
    Practise it in Tendra Tents: Kestrel contract: limits of the break-even analysis
  3. (c) Discuss28% of the task

    Core activity E: Short-term decisions
    What it asked
    How weighted benefit scoring would be used to support the in-house or outsource decision.
    Stronger answers
    Walked through the method (choose criteria, weight them, score each option, compare weighted totals) with criteria and weights that suit this particular decision.
    Weaker answers
    Listed general non-financial factors and left out the scoring process altogether.
    Practise it in Tendra Tents: Tendra Care: checking the weighted benefit scoring

Task 2

Trigger: In-house production goes ahead. The new facility needs budgets, and because it will make dips for stock rather than to order, it will hold finished goods inventory.

  1. (a) Discuss36% of the task

    Core activity B: Budgeting
    What it asked
    Why production budgets will help the facility's new production manager plan, co-ordinate and control.
    Stronger answers
    Framed every purpose around the new manager and the new facility, including co-ordination between departments inside SoPa.
    Weaker answers
    Gave the generic purposes of budgeting, and some wrote about co-ordinating with outside parties instead of within the business.
    Practise it in Tendra Tents: Retail budget request: effect on planning and control
  2. (b) Discuss32% of the task

    Core activity B: Budgeting
    What it asked
    How to build the production, raw materials usage and raw materials purchases budgets from the cost card provided.
    Stronger answers
    Set out how each budget is built, including opening and closing inventory, and made it a discussion with points such as how to decide inventory levels, using the cost card.
    Weaker answers
    Gave vague steps, ignored inventory movements or simply repeated the cost card.
    Practise it in Tendra Tents: Retail budget request: effect on planning and control
  3. (c) Apply32% of the task

    Core activity D: Reporting, ethics and tax
    What it asked
    How the inventory standard (IAS 2) values the facility's finished goods.
    Stronger answers
    Stated the lower of cost and net realisable value, explained how each is found, and applied that to the suggestions about cost and to dips with a short shelf life.
    Weaker answers
    Showed a partial grasp of the rule or of how cost and net realisable value are found, with little application.
    Practise it in Tendra Tents: Spring build: valuing inventory at the half-year

Task 3

Trigger: Management weighs absorption costing against activity based costing for the facility, and a manager suggests using the economic order quantity model to decide how many glass jars to order at a time.

  1. (a) Recommend, with justification20% of the task

    Core activity A: Costing
    What it asked
    An overhead absorption basis for each of the three production processes in the schedule.
    Stronger answers
    Gave one sensible basis per process, each justified from the information in the schedule.
    Weaker answers
    Named sensible bases without saying why they fit, or gave vague bases with thin reasons.
    Practise it in Tendra Tents: Spring build: why December's profit depends on the costing method
  2. (b) Evaluate32% of the task

    Core activity A: Costing
    What it asked
    Whether activity based costing suits the new facility.
    Stronger answers
    Knew when ABC earns its keep (complex production, many products, a high share of overheads) and tested that against the dips facility.
    Weaker answers
    Explained how to apply ABC to the schedule instead of whether it suits, or gave the theory without evaluating it.
    Practise it in Tendra Tents: Premium range: reading the ABC results
  3. (c) Explain16% of the task

    Core activity F: Working capital
    What it asked
    What the EOQ represents and the information needed to calculate it.
    Stronger answers
    Explained what the EOQ balances and defined annual demand, cost per order and holding cost per unit.
    Weaker answers
    Showed little technical understanding, or left it out.
    Practise it in Tendra Tents: Spring build: fabric inventory and the EOQ model
  4. (d) Recommend, with justification32% of the task

    Core activity F: Working capital
    What it asked
    Whether the EOQ model is a sound way to decide how the facility orders its glass jars.
    Stronger answers
    Tested the model's assumptions one by one against buying jars for this facility and gave a recommendation that reflected how uncertain those assumptions are.
    Weaker answers
    Mentioned even production and little else, and the recommendation was not justified.
    Practise it in Tendra Tents: Spring build: fabric inventory and the EOQ model

Task 4

Trigger: A few months in, the facility's production variances and a KPI dashboard are ready for a month, and the Finance Director wants the dashboard to cover sustainability.

  1. (a) Interpret76% of the task

    Core activity C: Performance
    What it asked
    What each production variance says about the month's performance, using the email notes and the dashboard.
    Stronger answers
    Said exactly what each favourable or adverse variance means, gave reasons drawn from the email, used the dashboard and summed up overall performance.
    Weaker answers
    Explained how to calculate the variances, or gave imprecise meanings (a material price variance that could mean price per kilo or quantity used), with reasons not taken from the case.
    Practise it in Tendra Tents: Spring build: interpreting April's sales variances
  2. (b) Recommend, with justification24% of the task

    Core activity C: Performance
    What it asked
    Two sustainability KPIs to add to the facility's dashboard.
    Stronger answers
    Two SMART measures linked to sustainability, each justified for this facility.
    Weaker answers
    Measures that were not SMART, or that repeated the waste KPIs already on the dashboard.
    Practise it in Tendra Tents: Online channel: analysing the Q4 dashboard

Common mistakes

  • Describing the profit–volume chart instead of interpreting it and comparing the options.
  • Explaining how ABC would be applied when the sub-task asked whether it was suitable.
  • Giving the calculation of a variance instead of its meaning and its cause.
  • Suggesting KPIs the dashboard already measured.
  • Recommending without justifying, on absorption bases and on EOQ.

Lessons for any pre-seen

  • Interpret a chart by stating what each element tells you and then comparing the options; calculation is not needed unless asked.
  • For a suitability question, test the method's conditions or assumptions against the facts and answer whether, not how.
  • Make each variance precise: price per unit of input and quantity used are different stories.
  • Before recommending a KPI, check what is already measured, then make yours SMART.
  • When a task names a reader, such as a new manager, write for that person.

For the patterns across all 6 variants, read the SoPa examiner's report summary.

Sources

CIMA, Operational Case Study, May and August 2026: full post-exam materials (PDF). Page numbers are the PDF's own; each link opens the first page of the range.

The same materials are listed on CIMA's post-exam materials page for May & Aug 2026. Checked on 20 October 2026.

Practise the same skills in Tendra Tents

Timed OCS tasks in the current pre-seen, marked against the same four elements. Try one marked task free, no card needed.

Core is £149 and Premium is £249, one payment per level.

Not ready to try a task? Tell us why. One question, no email.
What would stop you?